Network Rail Results

About Network Rail

Network Rail undertakes to ‘provide the best possible service to everyone who relies on the railway’, and add that this means ‘delivering a safer, more reliable railway with greater capacity and efficiency than ever before’.  When you consider that Network Rail owns and operates 20,000 miles of track, 40,000 bridges tunnels and viaducts and thousand of signals, level crossings and stations, you begin to realise the scale of what they have committed themselves to!

The constant rise in the number of passengers is putting an increasing demand on the rail infrastructure, which in turn is causing the performance of rail companies to become the subject of a lot of media and public scrutiny.  As a result of this, all types of rail companies are looking for ways to improve their performance…and are finding it a challenge!

Network Rail Logo PNG - Clarity Visual Management

The Network Rail Challenge

In 2014, Network Rail’s London North East (LNE) line made a serious re-evaluation of just what it was going to take to meet and exceed these challenges, and as a result of this, the SMART programme was born. Network Rail contracted John Hargaden Associates (now known as Harmona Consulting) as Lean Consultants, and Clarity Visual Management as visual management implementers, resulting in Clarity working as a go-between to them both, to provide the dynamic, quick changing visual management that JHA dictated, and that Network Rail so much needed.

The challenges were enormous. In 2014, LNE was employing 4,132 people spread over numerous locations. Changing the culture and mindset was not going to be an easy task.  Fortunately, there were some advanced Lean thinkers already within the senior management of LNE, and they quickly realised that a traditional ‘top-down’ (pressure put on the workforce by the management) approach was not going to work.  However, they also identified that a purely ‘bottom up’ (pressure put on the management by the workforce) approach was not effective either … they needed to work together to really embed a culture of Lean throughout such a diverse and complicated organisation.

Clarity Visual Management Network Rail Case Study Workers

Clarity’s Support & Expertise…

WOW (Walk Out Wednesdays)

WOW (Walk Out Wednesdays) were quickly implemented, where the office staff, including the management, left their offices and visited the track, the stations, etc, and ideas and suggestions were freely exchanged at all levels. This was a great move toward closing the gap between the front line and the ‘ivory towers’ and engendered a level of mutual respect that had never been known before.

Control Rooms

Clarity Visual Management helped Network Rail to set up well over five hundred individual control rooms, which became the nerve centres of the SMART programme. These simple rooms were sometimes a spare office, often a Portakabin, even a section of corridor that could be closed off, anywhere that could be designated an area where attention could be focussed on the key data, the results, successes, challenges away from the distraction of the everyday.

Wherever the location, each room was of consistent style – lined with whiteboards covered with Clarity Magnetic Overlays which were monitoring the status of the operations on a daily basis.  All the activities were controlled from this point using a simple Plan Do Check Act (PDCA) method. A Control Room Meeting was set up at least once a week in the Control Room, each meeting following a consistent pattern and with everybody focussed on improving the business.

Clarity Network Rail Control Room

Obviously, the detailed content of each control room varied according to the operations of the relevant team, but the basic structure was the same:

 

  • Headline Board – monitoring the status of the key projects against a given target on a time basis
  • Meeting Actions Board – to record the actions required as a result of the meeting, who they were assigned and when the completion date was to be
  • Health, Safety and Environment Board – to ensure that any concerns or ideas for improvement are captured and actioned in this all-important area
  • Control Room Specific Detail Boards – boards that were specific to the operation of the team to which the control room belonged. There are literally thousands of these, controlling everything from 5S to hotel accommodation for travelling workers
  • Purpose and Rules of the Control Room – a reminder of the most effective way to run a control room meeting

 

All of these were produced as individual designs for each control room.  Rarely were two produced exactly the same. Sometimes only minor tweaks were necessary to an existing board … a project title, location and the number of personnel, all varied from one control room to the next and it was important that every single board should be as relevant and as tailored to the needs of its users as possible.

In addition to this, particularly in the early days of the SMART programme, John Hargaden’s team of consultants were changing and tweaking their methods on a daily basis and required an exceptionally swift system for changing the design of the boards.

We set to develop a professional looking, easily replaceable and cost-effective solution … and the Clarity Magnetic Overlay was born!  The overlays could be easily installed just by laying them onto a standard magnetic whiteboard which were in abundance throughout Network Rail. Our solution was very cost-effective and could be produced in just 3 to 4 days, even soon if exceptional deadlines required it … ticking all the boxes for dynamic Continuous Improvement in a fast-changing environment.  We were, at the time, regularly working on 10 or more control rooms at a time and these overlays also had the huge advantage that they could be economically posted or even rolled up and taken by the consultants or Network Rail staff on trains.

Clarity Visual Management Magnetic Overlay

 

Network Rail Selector Website

In a short space of time, we had produced over 4000 different designs for Network Rail’s control rooms. Whilst we were very anxious that each board should be precisely focussed to the needs of its users, there were many occasions where an existing board or part of a board exactly fitted another situation and we were anxious not to introduce the waste we were trying to remove by re-creating existing designs! It was clearly necessary that all the relevant staff should be able to access a library of everything that had been produced and to meet this need, we launched the Network Rail Selector website.

This was a private area of our website, requiring strict log-on procedures, where a library of all artwork was available, segregated into control room types.  A user could simply log on and either raise a requisition directly from the website, or download the nearest artwork, change it according to their own needs, and raise a requisition through their normal channels.  This proved immensely beneficial to all users and helped to control what could have become an unmanageable volume of designs efficiently and without wastage.

Clarity Visual Management Network Rail Portal

“Clarity magnetic overlays have played an important part in our visualisation success in LNE, and are essential to allow the boards to evolve with the program without unnecessary costs.”

Phil Verster, Managing Director of LNE

And the results…?

The figures speak for themselves:

 

  • Operations and Maintenance Expenditure decreased from £180 million pa to £166 million
  • Maintenance expenditure decreased from £110 million to £107 million pa
  • 20% Reduction in Workforce Accidents and Irregular Working Incidents

 

Clarity Visual Management Network Rail Control Room

We were also delighted to read the official report from the Office of Rail and Road (ORR) on Network Rail, as follows:

  • Operators using the East Coast Mainline have seen performance for the last few periods of 2014-15 well above previous levels
  • Train cancellations East Coast Mainline performance has been strong – the three long-distance operators on this route all exceeded their cancellation and severe lateness (CaSL) targets. However, performance for many operators on other routes is behind plan
  • There are, however, indications that the overall downward trend seen since the latter part of 2011-12 may have been halted. Operators using the East Coast Mainline have seen performance for the last few periods of 2014-15 well above previous levels

The recent performance of the East Coast Mainline has been a success. Three of the four long distance operators on this route exceeded their PPM and CaSL targets and these are the best performing operators in terms of variance against both measures.

 

From:  Office of Rail and Road Network Rail Monitor Quarters 3-4 of Year 1 of CP5.  This publication is licensed under the terms of the Open Government Licence v3.0 except where otherwise stated.  See http://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/

Note:  East Coast Mainline is the same as the London North East (LNE) Route

Our other case studies

BLE Lighting

E & R Group

Jotun Paints

QJS (UK) Ltd: Food Hygiene Systems & Equipment

Stonegate Precision Tooling

Toyota Manufacturing UK

DPD

Crown Paints

Huntsman IFS Chemicals

NHS Hospital

Contact us

Contact us

Get in touch and speak with a Visual Management Specialist to answer any questions you may have on our products, consultancy or business.

Enquire now

Book An Initial Consultation Today

Book An Initial Consultation Today

Is your business achieving its full potential? Clarity offers a proven approach to help your business achieve its vision. Book now!

Make appointment

Our brochure

Our brochure

To explore more about Clarity Visual Management, get a copy of our latest introductory brochure to learn more about our service.

View brochure

E-bulletin

Receive our monthly e-bulletin containing information, news, ideas, promotions and case studies.

Contact Form
Click to Call
View Brochure